The investigation report into the fire at the electricity transformation stations in Nouakchott revealed that accumulated deficiencies by the Ministry of Energy, Société Mauritanienne de l'Électricité (SOMELEC), and the contracting companies led to the fire that plunged the capital into darkness for days. The incident resulted in economic losses estimated at around 11 million dollars, due to neglect of safety and monitoring procedures. The committee recommended taking strict measures, including contract termination and enhanced safety protocols, to prevent the recurrence of such incidents and ensure the stability of the electricity network in Mauritania.