The Ministry of Public Works and Transport clarifies that work in the Al-Fayadiyah area initially began to address a pothole and resurface the damaged road. However, the scope of the work was expanded after a significant leak was discovered in one of the main water lines, necessitating an intervention to repair the fault. Additionally, high-voltage electrical lines were found buried underground, which required special coordination with the relevant authorities to ensure safety and prevent further excavations. As a result, the project now involves joint coordination among multiple departments, taking additional time to complete the repairs safely. Coordination efforts are ongoing to accelerate the project's progress once the water and electricity networks have been addressed.