The Ministry of Public Works and Transport clarifies that the extension of work in Al-Fayadiyah was due to the expansion of the project following the discovery of a significant leak in the main water line, which necessitated repair. The project also included organizing work on the high-voltage underground electrical network, requiring careful coordination with relevant authorities to ensure safety and adhere to technical arrangements. As a result, the operations went beyond simply repairing a pothole and paving the road; they now required coordination between multiple entities and a technical team, adding extra time to complete the work properly and safely. The ministry emphasizes its ongoing cooperation with concerned parties to expedite the project, with the completion of water and electricity network repairs to ensure the full reopening of the road.